Current as of 1:11 p.m. CT Wednesday, Nov. 18, 2026.
In one sentence: The state has restarted its environmental permit reviews for data centers, but Lubbock’s own decision on a 90-day pause is still on the City Council’s calendar for Dec. 10.
The state just took its foot off the brake on data center permits. Lubbock hasn’t decided yet whether to press its own.
The Texas Commission on Environmental Quality, the state agency that handles air-pollution permits and construction stormwater permits, has resumed reviewing permits tied to data center projects. That ends a pause Gov. Greg Abbott ordered this fall, The Texas Tribune’s Emily Foxhall reported in a story also carried by The Associated Press. For Lubbock, the state’s move and the city’s proposed pause are two separate tracks. Here’s how they fit together.
The short version
- What changed: TCEQ told the Tribune it is back to its normal permit review process and will judge applications under all applicable state and federal laws and regulations, according to a written statement from spokesperson Laura Lopez.
- Why now: The agency got notice from Abbott’s office on Friday, Nov. 13, that officials at ERCOT, the state’s main power grid operator, had finished gathering information on possible community impacts from data centers.
- What’s still coming: ERCOT’s full findings aren’t out. It plans to deliver them to the Public Utility Commission on Dec. 10 and discuss them at the PUC’s Dec. 17 open meeting.
- In Lubbock: The City Council is still considering a proposed 90-day pause on new applications tied to large-scale data centers, with a second public hearing set for Dec. 10, the Lubbock Chronicle reported Wednesday.
What it means for Lubbock
The state decision doesn’t settle anything at City Hall. TCEQ’s permits deal with air emissions and runoff from construction sites. Lubbock’s proposed moratorium, which grew out of a citizen petition organized by SAVE Lubbock, would temporarily stop the city from accepting, processing and approving new rezoning, permit and annexation applications for large-scale data centers. City Planning Director Kristen Sager told us earlier this month the pause can’t be retroactive, so applications already filed wouldn’t be covered. Our hearing preview has more on how it would work.
We have not seen any report that a specific Lubbock-area project has received, or is waiting on, a TCEQ permit since the pause ended. We’ll update this story if that changes.
One date to circle: Dec. 10 is both the council’s second hearing on the pause and the day ERCOT is targeting to publish its final community-impact report, according to ERCOT’s Nov. 5 presentation.
How the state got here
In August, Abbott asked ERCOT and state electricity regulators to audit data centers trying to connect to the grid and collect information on tax incentives, power use, water use and neighborhood impacts. He also paused grid connection approvals for data centers during that review, according to the Tribune. A Sept. 21 letter then told TCEQ to wait on related environmental permits until ERCOT finished its review.
In October, Public Citizen and FracTracker Alliance flagged data center-related construction permits that were being cleared anyway. TCEQ said it suspended them and switched to paper applications reviewed by staff, the Tribune reported.
Abbott lost his reelection bid Nov. 3 to Democrat Gina Hinojosa, who said on the campaign trail she would keep data center approvals paused until lawmakers pass new state laws. Neither Abbott’s office nor Hinojosa’s team immediately answered the Tribune’s request for comment Tuesday.
What ERCOT has said so far
ERCOT sent its information request to 465 data center projects and heard back from 433 of them, about 93%, according to its Nov. 5 update. ERCOT said the answers were enough for a statistically meaningful analysis in its final report. Among the requests, ERCOT’s West Texas load zone accounted for the biggest share of requested power, about 41%.
Critics push back
Public Citizen responded by calling on TCEQ’s commissioners to resign. The group argued the agency restarted permits without sharing ERCOT’s findings with communities or explaining how those findings will shape permit decisions, the Tribune reported.
What’s next, at City Hall and in Austin
- Dec. 1: The council is scheduled to consider the Planning and Zoning Commission’s recommended data center zoning rules, covering things like where facilities can go, setbacks, noise, landscaping and eventual closure, according to The 806er and the Lubbock Chronicle. Our explainer on the P&Z rules walks through them.
- Dec. 10: Second public hearing on the 90-day pause, and the council’s first chance to vote on it. Sager told us a second and final vote would come in January.
- In Austin: State Sen. Charles Perry, R-Lubbock, has filed Senate Bill 338, which would set water-use and reporting standards for big new data centers. Here’s our SB 338 explainer.
- Tax breaks: A separate Tribune analysis found 53 local tax agreements covering 34 Texas data centers, worth more than $1 billion in local property tax breaks, the Lubbock Chronicle noted.
How to weigh in
You can sign up to speak at City Council meetings or email your council member. The city posts each agenda, with meeting times and sign-up rules, in its Agenda Center. We’ll keep following both the state and local decisions.
- Jadds Roofing & Complete Restoration (Roofing and gutter installation). Black Friday offer: Free roof inspections, $500 off a new roof with an insurance claim, plus $200 off seamless gutters. Call 806-319-4554.
- ProClear Water Solutions (Water softeners and filtration). Black Friday offer: 10% off and/or a free RO system with a water softener (through Dec. 20, 2026). Call 806-905-7042.
- Raider Flooring (Flooring, kitchen and bath, on 50th Street just west of Quaker). Black Friday offer: Buy one box, get the second box half off on special order material. Call 806-412-0746.
- Poopy Be Gone (Dog waste removal). Black Friday offer: Sign up for quarterly billing and get 10% off the invoice, a free initial cleaning ($99 value) and a free Fresh Yard Package for the first month ($50 value: yellow spot treatment, full-yard sanitizing and deodorizing). Use code BlackFriday2026. Call 806-316-5110.
Sources
- The Texas Tribune, Emily Foxhall, Texas regulators are resuming environmental permits for data centers, Nov. 17, 2026: https://www.texastribune.org/2026/11/17/tceq-environmental-data-center-permits-resume/
- The Associated Press (Texas Tribune story): https://apnews.com/article/environmental-regulators-texas-data-centers-58b175a57bbc2c90fe0c8fa0a5bb8944
- Lubbock Chronicle, Texas Resumes Data Center Permit Reviews as Lubbock Weighs a Pause, Nov. 18, 2026: https://www.lubbockchronicle.com/p/texas-resumes-data-center-permit-reviews-as-lubbock-weighs-a-pause
- Lubbock Chronicle, Residents Urge Lubbock Council to Pass 90-Day Data Center Moratorium, Nov. 11, 2026: https://www.lubbockchronicle.com/p/lubbock-data-center-moratorium-public-hearing-november-2026
- The 806er, Lubbock hears public comments on a data center pause, Nov. 11, 2026: https://the806ermedia.com/articles/lubbock-hears-public-comments-on-a-data-center-pause-with-a-second-hearing-set-f
- ERCOT, Data Center State and Community Impact RFI: Preliminary Summary, Nov. 5, 2026: https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf
- Hub City UnCovered, Nov. 10 council hearing preview: https://hubcityuncovered.com/lubbock-city-council-nov-10-2026-data-center-moratorium-hearing/
- Hub City UnCovered, P&Z data center rules explainer: https://hubcityuncovered.com/lubbock-data-center-rules-p-and-z-decision-council-nov-10-dec-1-how-to-speak-up/
- Hub City UnCovered, SB 338 explainer: https://hubcityuncovered.com/charles-perry-sb-338-data-center-bill-explained-lubbock-water-tax-breaks/